1. INTRODUCTION
Formwork is defined as
temporary structure whose purpose is to provide support and containment for
fresh concrete until it can support itself. It moulds the concrete to the
desired shape and size and controls its position and alignment. The development
of formworks is parallel with the growth of concrete construction throughout
the 20th century. The advancement of technology, increase of population and the
space limitation lead the way to construct high-rise buildings. But the task
was not very easy at the beginning but now the man made the task easy by
inventing new machinery and new techniques. The most important factor in terms
of cost, quality and speed in a high-rise building construction project is the
type of the formwork used in the project. The first formwork type to be used is
the conventional type formwork where the timber planks were supported on timber
columns. With the advancement of technology it developed gradually and people
used ply wood sheets instead of timber planks and steel pipes with jacks were
used to support the ply wood. Then people invented small units of formworks and
connect the repeating units in the construction. The larger units were invented
like formworks for slab panels, formworks for columns, beams etc. when the same
elements are repeating. Then finally the whole system of formwork is made and
initially the material used to it was steel and it was very heavy. Then the aim
was to reduce the weight of the system and the materials for formwork have
extended to aluminium, plastic, fibre glass etc.
Aluminium formwork system
provides aluminium formwork for RCC load bearing or RCC framed multi-storied
buildings and enables the walls and slabs to be poured in same operation. These
increases efficiency and also produces an extraordinarily strong structure with
excellent concrete finish. Due to the fine tolerance achieved in the machined
metal formwork components, consistent concrete shapes and finishes are obtained
floor after floor. This allows plumbing and electrical fittings to be prefabricated
with the certain knowledge that there will be an exact fit when assembled. As
described by the manufacturers a low-cost system for housing using aluminium
formwork. Aluminium formwork system is construction system for forming cast in
place concrete structure of building. It is also a system for scheduling and
controlling the work of other construction trends such as steel reinforcement,
concrete placement and mechanical and electrical conduits. This type of
construction requires a restructuring of the entire conventional construction
process to enable interaction between the design phase and production planning
in order to improve and speed up the construction. The speed of construction by
this system will surpass speed of most of the other construction method.
2. INNOVATION IN CONSTRUCTION
The traditional mode of
construction for individual houses comprising load bearing walls with an
appropriate roof above or reinforced concrete (RC) framed structure
construction with infill masonry walls would be totally inadequate for mass
housing construction industry in view of the rapid rate of construction.
Further, such constructions are prone to poor quality control even in case of
contractors with substantial resources and experience.
“For undertaking mass housing works, it is necessary to have innovative technologies which are capable of fast rate construction and are able to deliver good quality and durable structure in cost effective manner”.
Several systems are
adopted at different places in the world; eventually the systems which are
reasonably economical and easy for operation with skilled labor are useful in
India. Certain systems are in vogue and more and more contractors are trying to
bring in new technologies. These are essentially based on the basis of mode of
construction, namely, pre-cast construction or in-situ construction.
2.1 Cast-in-Situ Construction
Pre-cast and cast-in-situ
are techniques that are used for quick construction. Pre-cast includes the
wall-panel units and slab units directly added to building structure. The use
of aluminium also evolved as one of the technique for quick construction by use
of aluminium and steel (tunnel) formwork. As a matter of fact the cost of
the formwork may be up to 25% of cost of the structure in building work,
and even higher in bridges, it is thus essential that the forms are properly
designed to effect economy without sacrificing strength and efficiency.
Certain patented systems
based on imported technologies such as “Mascon System” (Canada), “Mivan System”
(Malaysia) have come on the Indian scene in recent years. In these systems
traditional column and beam construction is eliminated and instead walls and
slabs are cast in one operation at site by use of specially designed, easy to
handle (with minimum labor and without use of any equipment) light weight
pre-engineered aluminium forms. Rapid construction of multiple units of a
repetitive type can be achieved with a sort of assembly line production by
deployment of a few semi-skilled labors.
The entire operation
essentially comprises fitting and erecting the portion of shuttering as already
determined (the optimization in use is determined by appropriate planning) and
then carrying out concreting of the walls and slabs. Props are so designed that
they stay in position while de-shuttering of slabs and/or takes place. The
dimensional accuracy of the formwork is of high order. Therefore any
possibility of errors does not rise.
2.2 “3-S” SYSTEM OF PRECAST CONSTRUCTION
An engineered system of
building construction, namely “3-S” system was developed by B.G.SHIRKE
CONSTRUCTION TECH LTD., for achieving, speed, strength, safety and economy in construction practices. The system involves structural
elements such as pre-cast hollow column shells pre-cast concrete beams, light
weighed reinforced cellular autoclaved concrete slabs for floor and roofs
constituting the basic structural formwork. The “3-S” system involves
activities for construction of building such as:
I. Cast in-situ
sub-structure including foundations, stem columns, plinth beams, plinth
masonry.
II. Erection of partial
pre-cast components, jointing of these components using cast in-situ concrete
with appropriate reinforcement.
III. Lying of reinforced
cast in-situ screed over slab panels, construction of panels, construction of
walling, flooring, plastering, water proofing etc.
Achieving the “3-S” system in the MIVAN formwork is quite easy. MIVAN formwork has got the unsurpassed speed of construction due to saving time for required time in masonry and plastering. The strength of raw aluminium is very less but when alloyed with other materials prove to be strong enough to use as a formwork. To ensure safety in the site, an integrated safety/ working platform is developed which ensures labor safety during erection and striking of the formwork. Economy is also one of the main factors of any system. The MIVAN formwork proves to cost efficient as it can be used efficiently for 250 times.
3. FORMWORK
When concrete is placed, it is in plastic
state. It requires to be supported by temporary supports and castings of
desired shape till it becomes sufficiently strong to support its own weight.
This temporary casing is known as the formwork or forms or shuttering.
The term moulds is sometimes used to indicate formwork of relatively
small units such as lintels, cornices etc.
3.1 Definition of formwork
“Forms or moulds or
shutters are the receptacles in which concrete is placed, so that it will have desired
shape or outline when hardened. Once concrete develops the adequate strength
to support its own weight they can be taken out”.
“Formwork is the term given
to either temporary or permanent moulds into which concrete or similar
materials are poured”.
3.2 Requirements of a good formwork
The essential requirements
of formwork or shuttering are: -
a) It should be strong
enough to take the dead and live loads during construction.
b) The joints in the
formwork should be rigid so that the bulging, twisting, or sagging due to dead
and live load is as small as possible. Excessive deformation may disfigure the
surface of concrete.
c) The construction lines
in the formwork should be true and the surface plane so that the cost finishing
the surface of concrete on removing the shuttering is the least.
d) The formwork should be
easily removable without damage to itself so that it could be used repeatedly.
3.3 Types of Formwork
The material most commonly
being used to date is timber. However, due to the depleting forest reserves and
increasing cost of timber the use of alternate materials such as plywood and
steel has become prominent. More recently, materials such as plastics and
fiberglass are also being used for pre-fabricating formwork. The type of
material to be used depends on the nature of construction as well as
availability and cost of material. The constraints on the project such as
overall cost, time of completion also play a major role in the use of a
Particular material for formwork.
a) TIMBER FORMWORK
Timber is required for
practically all jobs of formwork. The timber bring used for formwork must
satisfy the following requirements. It should be durable and treatable. It
should have sufficient strength characteristics. It should be light weight and
well seasoned without warping. It should hold nails well. It is economical for
small construction jobs. It is design flexible and easy to erect. It has good
thermal insulation which makes it useful to be used in colder Regions. It can
easily be made into any shape or size. And it is easy for transporting purpose
for in between sites.
Fig 3.1Timber Formwork
b) STEEL FORMWORK
Mostly used in large
construction projects or in situations where large number of re-uses of the
same shuttering is possible. It is Suitable for circular or curved shaped
structures such as tanks, columns, chimneys etc. and also used for structures
like sewer tunnel and retaining wall. Strong, durable & have longer life.
Reuses can be assumed to vary from 100 to 120 wares timber varies from 10 to
12.Steel can be installed & dismantled with greater ease & speed
resulting in saving in labour cost. Excellent quality of exposed concrete
surface obtained. No danger of formwork absorbing water from the concrete and
minimizing honeycombing.
Fig 3.2 Steel Formwork
c) PLASTICS FORMWORK
These forms have become
increasingly popular for casting unique shapes and patterns being designed in
concrete because of the excellent finish obtained requiring minimum or no
surface treatment and repairs. Different types of plastic forms are available
like glass reinforced plastic, fiber reinforced plastic and thermoplastics etc.
The material allows greater freedom of design. Unusual textures and designs can
be molded into the form. It allows the contractor to pour structural and
finished concrete simultaneously. Because sections can be joined on the job
site in such a way so as to eliminate joints, there is no size limitation. If
carefully handled, a number of reuses are possible making it highly&
Economical. It is lightweight and easily stripped. The disadvantage of using
plastic forms is that it does not lend itself to field fabrication hence, the
design and planning of this form must be carefully carried out. Also care must
take not to damage the plastic by the heat applied for accelerated curing of
the concrete. Trough and waffle units in fiberglass are used in construction of
large floor areas and multistoried office buildings.
Fig 3.3 Plastic Formwork
d) ALUMINIUM FORMWORK
Forms made from aluminum
are in many respects similar to those made of steel. However, because of their
lower density, aluminum forms are lighter than steel forms, and this is their
primary advantage when compared to steel. As the strength of aluminum in
handling, tension and compression is less than the strength of steel, it is
necessary to use large sections. The formwork turns out to be economical if
large numbers of reuses are made in construction. The major disadvantage of
aluminum forms is that no changes can be made once the formwork is fabricated.
Fig 3.4 Aluminium Formwork
3.4 Loads acting on Formwork
In Construction, the
formwork has to bear, besides its own weight, the weight of wet
concrete, the live load due to labor, and the impact due to pouring concrete and workmen on it. The vibration caused due to vibrators used to compact the concrete should also be taken care off. Thus, the design of the formwork is an essential part during the construction of the building.
concrete, the live load due to labor, and the impact due to pouring concrete and workmen on it. The vibration caused due to vibrators used to compact the concrete should also be taken care off. Thus, the design of the formwork is an essential part during the construction of the building.
For the design of planks
and joists in bending & shear, a live load including the impact may be
taken as 370kg/m². It is however, usual to work with a small factor of safety
in the design of formwork. The surfaces of formwork should be dressed in such a
manner that after deflection due to weight of concrete and reinforcement, the
surface remains horizontal, or as desired by the designer. The sheathing with full
live load of 370 kg/m² should not deflect more than 0.25 cm and the joists with
200kg/m² of live load should not deflect more than 0.25cm.
In the design of formwork
for columns or walls, the hydrostatic pressure of the concrete should be
taken into account. This pressure depends upon the quantity of water in the
concrete, rate of pouring and the temperature.
The hydrostatic
pressure of the concrete increases with the following cases:-
· Increase in quantity of
water in the mix.
· The smaller size of the aggregate
· The lower temperature.
· The higher rate of pouring concrete
· The smaller size of the aggregate
· The lower temperature.
· The higher rate of pouring concrete
If the concrete is poured
in layers at an interval such that concrete has time to set, there will be very
little chance of bulging. Aluminium as usual is not a very strong material. So
the basic elements of the formwork system are the panel which is a framework of
extruded aluminium sections welded to an aluminium sheet. It consists of high
strength special aluminium components. This produces a light weight panel with
an excellent stiffness-to-weight ratio, yielding minimal deflections when subjected
to the load of weight concrete. The panels are manufactured in standard sizes
with nonstandard elements produced to the required size and size to suit the
project requirements.
4. MIVAN: - A Versatile Formwork
The system of aluminum
forms (MIVAN) has been used widely in the construction of residential units and
mass housing projects. It is fast, simple, adaptable and cost – effective. It
produces total quality work which requires minimum maintenance and when
durability is the prime consideration. This system is most suitable for Indian
condition as a tailor–made aluminum formwork for cast–in–situ fully concrete
structure.
4.1 Background
Mivan is basically an
aluminium formwork system developed by one of the construction company from
Europe. In 1990, the Mivan Company Ltd from Malaysia started the manufacturing
of such formwork systems. Now a days more than 30,000 sq m of formwork used in
the world are under their operation. In Mumbai, India there are number of
buildings constructed with the help of the above system which has been proved
to be very economical and satisfactory for Indian Construction Environment.
The technology has been
used extensively in other countries such as Europe, Gulf Countries, Asia and
all other parts of the world. MIVAN technology is suitable for constructing
large number of houses within short time using room size forms to construct
walls and slabs in one continuous pour on concrete. Early removal of forms can
be achieved by hot air curing / curing compounds. This facilitates fast
construction, say two flats per day. All the activities are planned in assembly
line manner and hence result into more accurate, well – controlled and high
quality production at optimum cost and in shortest possible time.
In this system of formwork construction, cast
– in – situ concrete wall and floor slabs cast monolithic provides the
structural system in one continuous pour. Large room sized forms for walls and
floors slabs are erected at site. These forms are made strong and sturdy,
fabricated with accuracy and easy to handle. They afford large number of
repetitions (around 250). The concrete is produced in RMC batching plants under
strict quality control and convey it to site with transit mixers.
The frames for windows and
door as well as ducts for services are placed in the form before concreting.
Staircase flights, facade panels, chajjas and jails etc. and other
pre-fabricated items are also integrated into the structure. This proves to be
a major advantage as compared to other modern construction techniques.
The method of construction
adopted is no difference except for that the sub – structure is constructed
using conventional techniques. The super–structure is constructed using MIVAN
techniques. The integrated use the technology results in a durable structure.
4.2 Modular Formwork
The formwork system is
precisely-engineered system fabricated in aluminium. Using this system, all the
elements of a building namely, load bearing walls, columns, beams, floor slabs,
stairs, balconies etc can be constructed with cast in place concrete. The
resulting structure has a good quality surface finish and accurate dimensional
tolerances. Further, the construction speed is high and the work can be done in
a cost effective manner.
The modular nature of the
formwork system allows easy fixing and removal of formwork and the construction
can proceed speedily with very little deviation in dimensional tolerances.
Further, the system is quite flexible and can be easily adapted for any
variations in the layout.
The availability of
concrete from ready mix concrete facility has augured well for the use of this
work system. However, the proliferation of RMC facilities in the cities in
India and the willingness to use mechanized means of transport and placing of
concrete, the use of aluminium formwork system has received a boost. The
quality of the resulting concrete is found to be superior.
Structurally speaking, the
adoption of the closed box system using monolithic concrete construction has
been found to be the most efficient alternatives. The stresses in both the
concrete and steel are observed to be much lower even when horizontal forces
due to wind or earthquake are taken into consideration.
The formwork system can be
used for construction for all types of concrete systems, that is, for a framed
structure involving column beam –slab elements or for box-type structure
involving slab-walls combination.
4.3 FORMWORK – COMPONENTS
The basic element of the
formwork is the panel, which is an extruded aluminium rail section, welded to
an aluminium sheet. This produces a lightweight panel with an excellent
stiffness to weight ratio, yielding minimal deflection under concrete loading.
Panels are manufactured in the size and shape to suit the requirements of
specific projects. The panels are made from high strength aluminium alloy with
a 4 mm thick skin plate and 6mm thick ribbing behind to stiffen the panels.
The panels are
manufactured in MIVAN’S dedicated factories in Europe and South East Asia. Once
they are assembled they are subjected to a trial erection in order to eliminate
any dimensional or on site problems.
All the formwork
components are received at the site whining three months after they are
ordered. Following are the components that are regularly used in the
construction.
4.3.1 WALL COMPONENTS
1) Wall Panel: - It forms the face of the wall. It is an Aluminium sheet properly cut to fit the exact size of the wall
FIG 4.1 WALL PANEL
2) Rocker: - It is a supporting component of wall. It is L-shaped panel having allotment holes for stub pin
FIG 4.2 ROCKER
3) Kicker: - It forms the wall face at the top of the panels and acts as a ledge to support.
FIG 4.3: KICKER
4) Stub Pin: - It helps in joining two wall panels. It helps in joining two joints
FIG 4.4 STUB PIN
4.3.2 BEAM COMPONENTS:
1) Beam Side Panel: - It forms the side of the beams. It is a rectangular structure and is cut according to the size of the beam
FIG 4.5 BEAM SIDE PANEL
2) Prop Head for Soffit Beam: - It forms the soffit beam. It is a V-shaped head for easy dislodging of the formwork.
FIG 4.6 PROP HEAD FOR SOFFIT BEAM.
3) Beam Soffit Panel: - It supports the soffit beam. It is a plain rectangular structure of aluminium.
FIG 4.7 BEAM SOFFIT-PANEL
4) Beam Soffit Bulkhead: - It is the bulkhead for beam. It carries most of the bulk load.
FIG 4.8 BEAM SOFFIT BULKHEAD
4.3.3 DECK COMPONENT
1) Deck Panel: - It forms the horizontal surface for casting of slabs. It is built for proper safety of workers.
FIG 4.9: - DECK PANEL
2) Deck Prop: - It forms a V-shaped prop head. It supports the deck and bears the load coming on the deck panel.
FIG 4.10 DECK PROP
3) Prop Length: - It is the length of the prop. It depends upon the length of the slab.
FIG 4.11 DECK PROP LENGTH
4) Deck Mid – Beam: - It supports the middle portion of the beam. It holds the concrete.
FIG 4.12 DECK MID-BEAM
5) Soffit Length: - It provides support to the edge of the deck panels at their perimeter of the room.
FIG 4.13 SOFFIT LENGTH
6) Deck Beam Bar: - It is the deck for the beam. This component supports the deck and beam.
FIG 4.14 DECK BEAM BAR
4.3.4 OTHER COMPONENTS
1) Internal Soffit Corner: - It forms the vertical internal corner between the walls and the beams, slabs, and the horizontal internal cornice between the walls and the beam slabs and the beam soffit.
FIG 4.15 INTERNAL SOFFIT CORNER
2) External Soffit Corner: - It forms the external corner between the components
FIG 4.16 EXTERNAL SOFFIT CORNER
3) External Corner: - It forms the external corner of the formwork system.
FIG 4.17 EXTENAL CORNER
4) Internal Corner: - It connects two pieces of vertical formwork pieces at their exterior intersections.
FIG 4.18 INTERNAL CORNERS
4.4 CONSTRUCTION ACTIVITIES WITH MIVAN FORMWORK
The construction
activities are divided as pre – concrete activities, during concreting and post
– concrete activities. They are as follows:
4.4.1 PRE – CONCRETE ACTIVITIES:
a) Receipt of Equipment on Site – The equipments is received in
the site as ordered.
b) Level Surveys – Level checking are made to maintain horizontal
level check.
c) Setting Out – The setting out of the formwork is done.
d) Control / Correction of Deviation – Deviation or any correction
are carried out.
e) Erect Formwork – The formwork is erected on site.
f) Erect Deck Formwork – Deck is erected for labours to work.
g) Setting Kickers – kickers are provided over the beam.
After the above activities
have been completed it is necessary to check the following.
i. All formwork should be cleaned and coated with approved realize agent.
ii. Ensure wall formwork is erected to the setting out lines.
iii. Check all openings are of correct dimensions, not twist.
iv. Check all horizontal formwork (deck soffit, and beam soffit etc.) in level.
v. Ensure deck and beam props are vertical and there is vertical movement in the prop lengths.
vi. Check wall ties, pins and wedges are all in position and secure.
vii. Any surplus material or items to be cleared from the area to be cast.
viii. Ensure working platform brackets are securely fastened to the concrete.
Fig 4.19 Fixing Mivan
Plates
4.4.2 ON CONCRETE ACTIVITIES:
At least two operatives
should be on standby during concreting for checking pins, wedges and wall ties
as the pour is in progress. Pins, wedges or wall ties missing could lead to a
movement of the formwork and possibility of the formwork being damaged. This –
affected area will then required remedial work after striking of the formwork.
Things to look for during concreting:
i. Dislodging of pins / wedges due to vibration.
ii. Beam / deck props adjacent to drop areas slipping due to vibration.
iii. Ensure all bracing at special areas slipping due to vibration.
iv. Overspill of concrete at window opening etc.
Fig 4.20 Concreting Work
of Column, Beam, Slab
4.4.3 POST – CONCRETE ACTIVITIES:
i) Strike Wall Form- It is required to strike down the wall form.
ii) Strike Deck Form- The deck form is then removed.
iii) Clean, Transport and stack formwork
iv) Strike Kicker Formwork – The kicker are removed.
v) Strike wall – Mounted on a Working Platform the wall are fitted
on next floor.
vi) Erect Wall – Mount Working Platform and the wall is erected.
Normally
all formwork can be struck after 12 hours. The post – concreting activities
includes:
4.4.4 CLEANING:
All components should be
cleaned with scrapers and wire brushes as soon as they are struck. Wire brush
is to be used on side rails only. The longer cleaning is delayed, the more
difficult the task will be. It is usually best to clean panels in the area
where they are struck.
4.4.5 TRANSPORTING:
There
are basic three methods recommended when transporting to the next floor:
i. The heaviest and the longest, which is a full height wall panel, can be carried up the nearest stairway.
ii. Passes through void areas.
iii. Rose through slots specially formed in the floor slab for this purpose. Once they have served their purpose they are closed by casting in concrete filter
4.4.6 STRIKING:
Once cleaned and transported to the next point of erection, panels
should be stacked at right place and in right order. Proper stacking is a clean
sign of a wall – managed operation greatly aids the next sequence of erection
as well as prevents clutters and impend other activities
Fig 4.21: - Erection of Platform
Fig 4.22:- Striking of formwork
Fig 4.23: - Positioning of Platform
Fig 4.24: - Removal of kicker
4.5 SPEED OF CONSTRUCTION
4.5.1 Work cycle
MIVAN is a system for scheduling &
controlling the work of other connected construction trades such as steel
reinforcement, concrete placements & electrical inserts. The work at site
hence follows a particular sequence. The work cycle begins with the deshuttering
of the panels. It takes about 12-15hrs. It is followed by positioning of the
brackets & platforms on the level. It takes about 10-15hrs simultaneously.
The deshuttered panels are
lifted & fixed on the floor .The activity requires 7-10hrs Kicker and
External shutters are fixed in 7 hrs. The wall shutters are erected in 6-8 hrs.
One of the major activity reinforcement requires 10-12 hrs. The fixing of the
electrical conduits takes about 10 hrs and finally pouring of concrete takes
place in these.
This is a well
synchronized work cycle for a period of 7 days. A period of 10-12 hrs is left
after concreting for the concrete to gain strength before the beginning of the
next cycle. This work schedule has been planned for 1010-1080 sq m of formwork
with 72-25cu m of concreting & approximate reinforcement.
The formwork assembling at
the site is a quick & easy process. On leaving the MIVAN factory all panels
are clearly labeled to ensure that they are easily identifiable on site and can
be smoothly fitted together using formwork modulation drawings. All formwork
begins from corners and proceeds from there.
The system usually follows
a four day cycle: -
Day 1: -The first activity consists of erection of vertical reinforcement bars and one side of the vertical formwork for the entire floor or a part of one floor.
Day 2: -The second activity involves erection of the second side of the vertical formwork and formwork for the floor
Day 3: - Fixing reinforcement bars for floor slabs and casting of walls and slabs.
Day 4: -Removal of vertical form work panels after 24hours, leaving the props in place for 7 days and floor slab formwork in place for 2.5 days.
4.6 FEATURES OF MIVAN FORMWORK
1) Sheet Thickness & Panel Sizes
• The concrete face of panels (Al Sheet) is 4 mm thick.
• Standard sizes of Panels are: 2000x600, 2000x300, 1200x300, 850x300.
• Apart from above any size as required shall be manufactured and delivered.
2) Load Carrying Capacity
• High load carrying capacity of 7-8 Tonnes Per square meter
• Weight
• Light weight is the main advantage over conventional formwork technology.
• Aluminium formwork weighs around 18-20 kg per meter square.
3) Cycle Time
High speed of construction
can be achieved by this system that means faster completion of project. 7 Days
per floor.
4) Striking time
• Vertical (Wall) Formwork – 12 hours after concreting or when concrete strength has reached 2N/mm2.
• Horizontal (Deck) Formwork – 36 hours after concreting or when concrete strength has reached 10N/mm2.
5) Pouring System
Monolithic pouring for:
• Slabs
• Walls
• Columns
• Beams
6) Durability
• The panels are made out of Structural Grade Aluminium alloy.
• Around 200 repetitions can be achieved while using Aluminium Formwork System.
4.7 Design Aspects
The comparison is done
between buildings constructed by: -
i) Conventional RC
columns, beams, and slab construction (RC moment resisting frame d structure)
OR
ii) RC load-bearing walls
and slabs.
In the case of RC
moment-resisting framed structures, the horizontal forces due to wind or
earthquake are resisted by the frames resulting in the bending moments in
columns to resist bending moment and vertical loads would be more than that
required to resist vertical loads without bending moment. Similarly, additional
reinforcement will be required in beams at supports. In the case of RC
load-bearing walls, monolithic casting of slab along with RC walls results in a
box type structure, which is very strong in resisting horizontal forces due to
wind or earthquake. In view of large depth of shear walls, the resulting
stresses due to bending moment and vertical loads are smaller and in many
cases, concrete alone is capable of resisting these forces.
On evaluating these
alternatives, it is seen that the beam column frame system in
i) Performs poorly against
earthquake forces compared to RCC wall and slab construction. Recent changes in
the IS Codes, as well as recommended good practice demand provision of additional
reinforcement comply with ductility requirements.
ii) The sizing and
detailing of columns needed to be –that they are 20% stronger than beams they
support.
4.8 ECONOMY
The cost per flat (or per
m² built up area) using MIVAN shuttering system depends upon the number of
repetition and period of completion of the project. As the formwork can be
reused over 250 times, the initial cost per unit of forming area is less when
compared to traditional methods. The reduction of cost is also due to the
elimination of brickwork and plaster and also due to reduction in time. The
cost of the project gets substantially reduced due to shear wall construction.
These are due to the reduced consumption of steel, masonry, and plaster even
though the use of concrete decreases. For the same number of repetition, the
cost will be less if the period of completion is longer. This is because for a
shorter completion period, the area of formwork is more than required for
longer completion period. Cost of formwork is illustrated in Table 4.1.
The aluminium formwork
provides an integrated scaffolding system which reduces the cost of scaffolding
requirements. The mechanical and electrical installation is simplified as
conduits are embedded in the structure by precise engineering of outlets and
service ducts. Thus, we can conclude that the overall cost of the project is
lesser when compared to project using traditional methods of formwork.
4.8.1 Cost comparison of mivan and conventional formwork
Initial cost of mivan
formwork is high when compared with conventional formwork. Mivan formwork is
economical when floors are typical and also labour cost for mivan is slightly
less when compared with conventional formwork. Aluminium formworks are more
durable, maximum repetition of 300 can be achieved where as in conventional
maximum repetition of 10 can be achieved which makes aluminium formwork more
economical.
Table 4.1 COST COMPARISON
Following the graphical
representation of the above study of rates at the different rates of formwork.
The chart shows the aluminium formwork is economical when the use of cycle. The
steel formwork is economical than the other formwork.
Fig 4.25 Cost Analysis Graph
4.9 Comparison of Aluminum Form Construction Technique over
Conventional Forms:
Table 4.2 Comparison Between Mivan and Conventional Form Work
5. HONEYCOMBING AND CRACKS IN SHEAR WALL
The mivan technology
follows monolithic construction i.e. all the structural member viz. beam, shear
wall, slab are casted at same time. In conventional construction the concrete
is placed from height of 0.6 to 1 meter, and that is what recommended height to
place the concrete. In Mivan Technology of construction the concrete is placed
from height of 3 meter in shear wall and compacted using vibrator, now as
height of placing concrete is more there are chances of segregation in concrete
resulting in honeycombing and cracks in wall. In mivan construction it is generally
happened that after removing formwork there is honeycombing in shear wall, in
this project we had tried to fix the problem of honeycombing in shear wall. We
had gone to BASF The chemical company pertaining this problem; they suggested
us to use the MasterGlenium ACE 30JP as admixture to concrete so as to increase
the workability of concrete to reduce honeycombing and increase the strength of
concrete. One of the measures to check the workability of concrete is its slump
and to check the strength is compressive strength. In this project we have
compared the slump and strength of concrete using admixture and no admixture by
slump cone test and compressive testing machine respectively. Following are the details.
A. Specification of MasterGlenium ACE 30JP
Appearance: Brownish
Liquid
Specific gravity -1.02 g/cm3
pH Value: 6-9
B. Concrete mix design
Grade designation: M35
Type of cement: OPC 53 Grade
Reduced water content for admixture: 20 %
Mix design
Conventional Concrete: 1:1.4:2.2
Concrete using admixture: 1:1.2:3.2
C. Slump cone test result
Table 4.3 SLUMP CONE TEST RESULT
D. Compressive strength testing result
Table 4.4 Compressive strength testing result
By using admixture the
workability of concrete is increased by 120 % whereas the strength of concrete
is increased by 13 %
6. THE ADVANTAGES AND DISADVANTAGES OF MIVAN:
6.1 Advantages:
The MIVAN formwork is
specifically designed to allow rapid construction of all types of architectural
layouts.
1) Total system forms the
complete concrete structure.
2) Custom designed to suit
project requirements.
3) Unsurpassed
construction speed.
4) High quality finish.
5) Cost effective.
6) Panels can be reused up
to 250 times.
7) Erected using unskilled
labor.
Quality and speed must be
given due consideration along with economy. Good quality construction will
never deter to projects speed nor should it be uneconomical. In fact, time
consuming repairs and modifications due to poor quality work generally delay
the job and cause additional financial impact on the project. Some experts feel
that housing alternatives with low maintenance requirements may be preferred
even if the initial cost is high.
6.2 LIMITATION OF MIVAN FORMWORK:
Even though there are so
many advantages of MIVAN formwork the limitations cannot be ignored. However
the limitations do not pose any serious problems. They are as follows: -
1) Because of small sizes finishing lines are seen on the concrete surfaces.
2) Concealed services become difficult due to small thickness of components.
3) It requires uniform planning as well as uniform elevations to be cost effective.
4) Modifications are not possible as all members are caste in RCC.
5) Large volume of work is necessary to be cost effective i.e. at least 200 repetitions of the forms should be possible at work.
6) The formwork requires number of spacer, wall ties etc. which are placed @ 2 feet c/c; these create problems such as seepage, leakages during monsoon.
7) Due to box-type construction shrinkage cracks are likely to appear.
8) Heat of Hydration is high due to shear walls.
7. CONCLUSION
The task of housing due to
the rising population of the country is becoming increasingly monumental. In
terms of technical capabilities to face this challenge, the potential is
enormous; it only needs to be judiciously exploited.
Civil engineers not only
build but also enhance the quality of life. Their creativity and technical
skill help to plan, design, construct and operate the facilities essential to
life. It is important for civil engineers to gain and harness the potent and versatile
construction tools.
Traditionally,
construction firms all over the world have been slow to adopt the innovation
and changes. Contractors are a conservative lot. It is the need of time to
analyze the depth of the problem and find effective solutions. MIVAN serves as
a cost effective and efficient tool to solve the problems of the mega housing
project all over the world. MIVAN aims to maximize the use of modern
construction techniques and equipments on its entire project.
We have tried to cover each
and every aspect related to aluminium (MIVAN) form construction. We thus infer
that MIVAN form construction is able to provide high quality construction at
unbelievable speed and at reasonable cost. This technology has great potential
for application in India to provide affordable housing to its rising
population.
Thus it can be concluded
that quality and speed must be given due consideration with regards to economy.
Good quality construction will never deter to projects speed nor will it be
uneconomical. In fact time consuming repairs and modification due to poor
quality work generally delay the job and cause additional financial impact on
the project. Some experts feel that housing alternatives with low maintenance
requirements may be preferred even if at the slightly may preferred even if at
the higher initial cost.
REFERENCES
1. IOSR
Journal of Mechanical and Civil Engineering (IOSR-JMCE), Miss. Patil
Dhanashri Suryakant1 , Prof. Desai D B
2.
International Journal of Innovative Research in Science, Engineering and
Technology
Vol. 3, Issue 6, June 2014, Patel Abhiyan S, Neeraj Sharma D, Bhavin K
Kashiyani.
3. International
Journal of Innovations In Engineering Research And Technology [IJERT] issn:
2394-3696 volume 2, issue 3
march2015, Mr. Shankar Bimal Banerjee.
4 Jain and
Jain., “(1993)”. “Design of Formwork”. “Design of Concrete Structures.”,
Edition 1993, pp 595-606.
5.
Kulkarni., D., V., “(2001)”. “ First Rate Forms”. “Times Journal
Construction and Design”. Oct-Dec 2001, pp 22-23.
6. International
Journal of Engineering and Technical Research, Kushal Patil, Ajitkumar
Jadhav, Nikhil Shingate
Thank you for a great article. The plastic formwork picture used in this article is that of our moladi plastic formwork system. Pity no mention or credit was given. Secondly, the disadvantage of using plastic forms is that it does not lend itself to field fabrication. This is not the case with moladi as the components are small and are assembled on site or field with ease and can also be removed and replaced if required Plastic is moulded at temperatures above 220 deg Celsius, Cement kicking off will therefore not have any negative effect on the plastic formwork.
ReplyDelete[admin] Thank you for the comment..
DeleteWhat is the loading percentage in such construction? How to calculate the built up area if the flat carpet area is 600sqft.
ReplyDeleteAs per this seminar report, carpet area will be 87.5% of plinth area. Hence plinth area corresponding to 600 sqft carpet area will be around 600/0.875 = 686 sqft.
DeleteFirst question is not clear.
what insulation materials can be used while using Mivan formwork? How would we integrate them and what would be the additional cost to it? Can you email me this information on manisha.shetty@cii.in
ReplyDeleteThank you for your enquiry. We will try to reply as soon as we get the information.
Delete